Project Title:
Boubyan Seaport Project (Phase 1-Stage 1) Design for Street Lighting, Landscaping and Irrigation Systems
Location: Boubyan Island, Kuwait
Owner: Ministry of Public Works
Project Cost : 400 M (USD)
Scope of Works: Design, Working Drawings and License approval
Description:
The project purpose is to design and construct a highway and a railway of approximate 30 km to connect Subiya and East Coast of Boubyan Island. It was a 4-Phase Project and works are divided to according to its scope of works. F&M in a joint venture with AECOM(International Office) to complete Phase 1 of the project Design for Street lighting, Landscaping and Irrigation System
 

Project Title:
Design and Planning for South Al-Jahra
Location: South AL-Jahra, Kuwait
Owner: Public Authority for Housing Welfare
Project Cost : 25 M (USD)
Project Duration : January 2008 - August 2008
Scope of Works: Design,Planning and Tender Documents for all Infrastructure Works
Description:

The project has a total of 4,000 total plot area divided into 400 sq.mts for every plot. The firm works for the provisions of water supply. Telecommunication, sewage, roads, street lighting, storm water, electrical fire protection and sanitary lines.

 

Project Title:
Planning and Infrastructure on Central Jail Area (Existing and New Area)
Location: Sulaibiya, Kuwait
Owner: Ministry of Interior
Project Cost : 36 M (USD)
Project Duration : June 2005 – February 2008
Scope of Works: Planning, License Approval, Infrastructure Works and Tender Documents
Description:
The project was divided into (2) two phase’s of Design stages. Phase I consists of Upgrading the Infrastructure for Electricity, Roads, Storm Water lines, Telecommunication lines Street lighting and other civil works. Phase II covers the new proposed planning to all infrastructure works. The design was divided into two-zonal functions. Zone 1 is the Secured Zone that requires high security level,includes Central Jail for men and Central Jail for women, Deportation Jail and Rehabilitation Center for Addicted Convict and a small area for future expansion, Operation building and many other structures that serves as the support facilities for the project. Zone 2 is the Non-Secured Area which didn’t required much security and open to public facilities consists of Mosque, Reception Building, parking areas and other related building and support facilities for the Ministry of Interior. An area for future expansion was also considered in planning.
 

Project Title:
Design for (14) Foot Bridge
Location: (Various Locations) Kuwait
Owner: Ministry of Public Works.
Project Cost : 4 M (USD)
Project Duration : June 2005 – 2008
Scope of Works: Design and Revision for the Working Drawings
Description:
In able to give proper and safe access for the pedestrian, Ministry of Public Works proposed foot bridged located in different areas of Kuwait. Application and various design was based accordingly to its individual location to accumulate not only the projects function and purpose but also to give aesthetical view.
 


Project Title:

Infrasturcture Works for joint of the Jleeb Al-Shuyokh

Location: Jleeh Al-Shuyokh, Kuwait
Owner: Public Authority for Housing Welfare
Project Cost : 6.2 M (USD)
Project Duration : September 2001 – June 2002
Scope of Works:
Study, Design and Planning for the main connection of all civil services. (Road, Storm Water, Sewage, Electrical and Telephone) with the Jleeb Al-Shuyokh Area.
 


Project Title:

Infrastructure Works for Al Shuhada Area


Location: Al-Shuhada,(South of Surra – Kuwait)
Owner: Ministry of Public Works
Project Cost : 6.2 M (USD)
Project Duration : September 2001 – June 2002
Scope of Works:
Shop Drawings for all civil works



 


Project Title:

Infrastructure Works for the Connection of  Al Doha
Location: Al-Doha, Kuwait
Owner: Public Authority for Housing Welfare
Project Cost : 6.2 M (USD)
Project Duration : September 2001 – June 2002

Scope of Works:

Study, Design and Planning for the main connection of all civil services (Road, Storm Water, Sewage, Electrical and Telephone) with the Al-Doha Area